BASIN CASTELLARO
Intervention summaryProject 10 “Bacino Castellaro” includes 2 resurgence systems: CR6-CR7-CR8, CR9. These have been treated, from the point of view of the interventions, as a single project.
The interventions consisted of actions aimed at maintenance, which provided for ordinary management with mowing of the grass once a year, purging interventions aimed at the removal of sediments from the bottom and the rearrangement of the bottom and the banks, redevelopment of the head of the spring and of the shaft downstream of the foreman for the first 100 meters.
Works implemented: Drainage and bank arrangement on both banks, realization of bank support, sediment removal and re-profiling of the riverbed on both banks.
Deviations from original plans / relevant notes: none